Denso Hall Rahguzar
On December 29th, the facade of Denso Hall Library is being cleaned by HF using our Herbal Reetha Soap Mix. Additionally, a special mud lime plaster is being prepared to plaster the trenches on Mariott Road.
Topics: eNews
On December 29th, the facade of Denso Hall Library is being cleaned by HF using our Herbal Reetha Soap Mix. Additionally, a special mud lime plaster is being prepared to plaster the trenches on Mariott Road.
Topics: eNews
On December 29th, 2020, the first segment of the terracotta cobble pavement on Marriot road was completed. The wiring work which started on 28th of December has moved to the next stage. K.E has started connecting wires to the recently installed pole. PTCL has shifted its booth connection to a new designated space.
Furthermore, the trenches on site that were previously lined by HF with bamboo panels have been plastered with mud lime plaster.
Topics: eNews
On December 28th, 2020 the underground wiring work for Denso Hall Rahguzar has started. Karachi Electric (K.E) has installed their required electrical post and PTCL (Telecommunications company) is in the process of taking the wires underground.
Furthermore, the trenches on site that were previously lined by HF with bamboo panels have been plastered with mud lime plaster.
Topics: eNews
On December 24th, 2020, HF has started the laying of terracotta cobbles at the Denso Hall Rahguzar - the first segment of the Red Trail that will connect the historic Denso Hall with Kharadar Chowk and the Custom House.
The radial pavement design centralizes around the 12” dia natural ceramic plaques carrying heritage images that are specially fabricated to dot the trail with reminders of Karachi’s glorious past.
The tiles are hand-made in Makli by HF’s Barefoot Entrepreneur women.
Topics: eNews
By December 1st, 2020, Imtiaz Naqvi Foundation successfully built and funded 3 LOG Shelters in Mirpur Khas, using our Youtube tutorials, online resources (and guidance from our project manager Mr. Naheem Shah).
Mirpur Khas is greatly affected by reoccurring flooding, resulting in loss of life and damage to personal properties, which leaves the villagers in a vulnerable state. On top of that, the cost of reconstruction of a house is unbearable for the affected ones.
LariOcta Green (LOG) has been designed as a flood-proof shelter. Using the quick assembly of prefab panels designed by the Heritage Foundation of Pakistan, Imtiaz Naqvi Foundation has managed to make each unit for Rs. 20,000.
Topics: eNews
Urdu News Coverage on Heritage Foundation of Pakistan’s Denso Hall Rahguzar Scheme in Mariott Road.
https://www.urdunews.com/node/522041?fbclid=IwAR1oOoy2M8lFKDVuDIfrK2273eGSFPW3gK6mEAGtim84rcSvSq42ip0IVRY
Topics: eNews
On November 18th, 2020, site work on Mariott road continues. Four new manholes are installed by KWSB and the process of covering underground cable trenches with bamboo panels has been initiated.
On November 24th, 2020, the DMC Douth Team is carrying out removal of existing pavement as well as any steps or floors that are built / projected out of the building lines. All residents and shop owners have been kindly requested to cooperate with them.
Topics: eNews
On November 11th 2020, Ar. Yasmeen Lari conducted a meeting at Denso Hall with representatives from Karachi Waterboard. They reviewed the work of water and sewerage drainage pipes that are being carried out at Mariott road.
One manhole and sub manhole has been constructed. On request of Ar. Yasmeen Lari, they have agreed on forming another two new manholes to replace two old ones.
Heritage Foundation has also started to cover the trenches and look to began working on covering the pavements with eco-friendly terracotta tiles.